Schedule
Working with the MSBA
Forming the Project Team
Forming the Project Team
Designer Selection
Issue RFS 2/5/2025
Submissions Due 3/5/2025
DSP Review 4/8/2025
DSP Interviews 4/22/2025
Execute Contract 5/21/2025
Feasibility Study
Feasibility Study
Duration: 12 Months
Target PDP Submission: December 2025
Target PSR Submission: April 2026
Schematic Design
Schematic Design
Duration: 8 Months
Target Submission: December 2026
Project Scope & Budget Agreement
Project Scope & Budget Agreement
Target Board Date: February 2027
Funding the Project
Funding the Project
District Approval & Votes
Target Date: TBD