Brockton High School

Construction Project

A once-in-a-generation investment in students,
educators, and the Brockton community

Schedule

Working with the MSBA

Forming the Project Team
Z
Forming the Project Team

Designer Selection

Issue RFS 2/5/2025

Submissions Due 3/5/2025

DSP Review 4/8/2025

DSP Interviews 4/22/2025

Execute Contract 5/21/2025

Feasibility Study
Feasibility Study

Duration: 12 Months

Target PDP Submission: December 2025

Target PSR Submission: April 2026

Schematic Design
Schematic Design

Duration: 8 Months

Target Submission: December 2026

Project Scope & Budget Agreement
Project Scope & Budget Agreement

Target Board Date: February 2027

Funding the Project
Funding the Project

District Approval & Votes

Target Date: TBD

Translate »